Purple Line Contractors

Contract 1: Elevated Structures (East)

The Works consist of the construction of precast prestressed concrete box girder viaduct approximately 12 km. in length and at an elevation of top of rail approximately 19 meters above existing ground, transition structure at Bang Sue, the construction of 8 stations (one is interchange station, Tao Poon), architectural works, the provision of building services facilities in the stations, the intermodel transfer (ITF) and the relocation, demolition and improvement works for the Metropolitan Electricity Authority (MEA) and other public utilities.

Contractor: CKTC Joint Venture, which comprises
                       Ch. Karnchang Public Co., Ltd.
                       Tokyu Construction Co., Ltd.

Notice to Commence: 10 November 2009

Construction Period: 1,350 days

Estimated Completion Date: 12 July 2013

 

Contract 2: Elevated Structures (West)

The Works consist of the construction of precast prestressed concrete box girder viaduct approximately 11 km. in length and at an elevation of top of rail approximately 19 meters above existing ground, a new railway bridge cross over the Chao Phraya River approximately 330 m. in length, and the construction of 8 stations, architectural works, the provision of building services facilities in the stations, the intermodal transfer (ITF) and the relocation, demolition and improvement works for the Metropolitan Electricity Authority (MEA) and other public utilities.

Contractor: Sino-Thai Engineering & Construction Public Company Limited

Notice to Commence: 1 March 2010

Construction Period: 1,350 days

Estimated Completion Date: 9 November 2013

 

Contract 3: Depot and Park & Ride Facilities

The Works consist of the construction of depot, workshop, train operation control center, train stabling for 48 trains (16 tracks) situated on platform (approximately area of 145,000 square meters) approximately 10 m. above road level, and 4 park & ride facilities at depot and along the route with approximate capacity of 1,800 cars (At depot), 1,950 cars (Sam Yaek Bang Yai), 1,100 cars (Tha It) and 450 cars (Yaek Nonthaburi 1).

Contractor: PAR Joint Venture, which comprises
                       Power Line Engineering Public Co., Ltd.
                       ASCON Construction Public Co., Ltd.
                       Ruamnakorn Construction (Thailand) Co., Ltd.

Notice to Commence: 1 March 2010

Construction Period: 1,350 days

Estimated Completion Date: 9 November 2013

 

Contract 4: Railway M&E Works Bang Yai to Tao Poon

The Works consist of provision signaling, traction and auxiliary power supply systems and substations, telecommunication systems, operation control centre facilities, workshop equipment, automatic fare collection system, platform screen doors, procurement of rolling stocks, etc.

Status: In the process of tender documents preparation.

 

Contract 5: Railway M&E Works Tao Poon to Bang Sue

The Works consist of provision signaling, traction and auxiliary power supply systems, telecommunication systems, automatic fare collection system, platform screen doors and other systems for the interchange station at Tao Poon, etc.

Status: In the process of tender documents preparation.

 

Contract 6: Track Works

The Works consist of provision track slab, rails, etc. approximately 23 km. along the line of the Project and in the depot also.

Status: In the process of tender announcement